FIRST DIVISION
[G.R. No. 141616. March 15, 2001]
CITY OF QUEZON, petitioner, vs. LEXBER INCORPORATED, respondent.
D E C I S I O N
YNARES-SANTIAGO,
J.:
Before us is a petition
for review on certiorari assailing the October 18, 1999 decision of the
Court of Appeals in CA-G.R. CV No. 59541[1] which affirmed in toto the January 26, 1998
decision of the Regional Trial Court of Quezon City in Civil Case No.
Q-94-19405.[2]
Briefly stated, the facts
are as follows –
On August 27, 1990, a
Tri-Partite Memorandum of Agreement[3] was drawn between petitioner City of Quezon,
represented by its then Mayor Brigido R. Simon, Jr., respondent Lexber, Inc.
and the then Municipality of Antipolo, whereby a 26,010 square meter parcel of
land located in Antipolo[4] was to be used as
a garbage dumping site by petitioner and other Metro Manila cities or
municipalities authorized by the latter, for a 5-year period commencing in
January 1991 to December 1995. Part of
the agreement was that the landowner, represented by respondent Lexber, shall
be hired as the exclusive supplier of manpower, heavy equipment and engineering
services for the dumpsite and shall also have the right of first refusal for
contracting such services.
This led to the drawing
of the first negotiated contract[5] between petitioner, represented by Mayor Simon, and
respondent Lexber on September 10, 1990, whereby the latter was engaged to
construct the necessary infrastructure at the dumpsite, designated as the
Quezon City Sanitary Landfill, for the contract price of P4,381,069.00. Construction of said infrastructure was
completed by respondent Lexber on November 25, 1991, and the contract price
agreed upon was accordingly paid to it by petitioner.
Meanwhile, on November 8,
1990, a second negotiated contract[6] was entered into by respondent Lexber with
petitioner, again represented by Mayor Simon, whereby it was agreed that
respondent Lexber shall provide maintenance services in the form of manpower,
equipment and engineering operations for the dumpsite for the contract price of
P1,536,796.00 monthly. It was further
agreed that petitioner shall pay respondent Lexber a reduced fee of fifty
percent (50%) of the monthly contract price, or P768,493.00, in the event
petitioner fails to dump the agreed volume of 54,000 cubic meters of garbage
for any given month. On December 11,
1991, respondent was notified by petitioner, through the City Engineer, Alfredo
Macapugay, Project Manager, Rene Lazaro and Mayor Simon to commence maintenance
and dumping operations at the site starting on December 15, 1991.[7]
Respondent Lexber alleged
that petitioner immediately commenced dumping garbage on the landfill site
continuously from December 1991 until May 1992. Thereafter, petitioner ceased to dump garbage on the said site for
reasons not made known to respondent Lexber.
Consequently, even while the dumpsite remained unused, respondent Lexber
claimed it was entitled to payment for its services as stipulated in the second
negotiated contract.
On December 12, 1992,
respondent’s counsel sent a demand letter to petitioner demanding the payment
of at least 50% of its service fee under the said contract, in the total amount
of P9,989,174.00. In view of the idle
state of the dumpsite for more than a year, respondent also sought a
clarification from petitioner regarding its intention on the dumpsite project,
considering the waste of equipment and manpower in the meantime, as well as its
loss of opportunity for the property.
Petitioner, this time
acting through Mayor Ismael A. Mathay, Jr. who succeeded Mayor Simon in the
interim, denied any liability under the contract on the ground that the same
was invalid and unenforceable.
According to Mayor Mathay, the subject contract was signed only by Mayor
Simon and had neither the approval nor ratification of the City Council, and it
lacked the required budget appropriation.
Thus, a complaint for
Breach of Contract, Specific Performance or Rescission of Contract and Damages
was filed by respondent Lexber against petitioner on February 21, 1994 before
the Regional Trial Court of Quezon City.
Respondent Lexber averred that because petitioner stopped dumping
garbage on the dumpsite after May 1992, Lexber’s equipment and personnel were
idle to its damage and prejudice.
Respondent prayed that petitioner be ordered to comply with its
obligations under the subject contract or, in the alternative, that the said
contract be rescinded and petitioner be ordered to pay damages.
On January 26, 1998,
after trial on the merits, the lower court rendered judgment in favor of respondent,
the dispositive portion of which states:
WHEREFORE, premises considered, judgment is hereby rendered in favor of the plaintiff and against the defendant:
1. Ordering the defendant to pay the plaintiff the amount of SEVEN HUNDRED SIXTY EIGHT THOUSAND FOUR HUNDRED NINETY THREE PESOS (P768,493.00) per month starting December 15, 1991 until December 31, 1995 with legal interest starting December 16, 1992, the date defendant received plaintiff’s extra-judicial demand, until defendant finally pays the entire amount;
2. Ordering defendant to pay costs of suit.
The claims for attorney’s fees and other damages are hereby denied for lack of merit.
SO ORDERED.[8]
On appeal to the Court of
Appeals, the said Judgment was affirmed in toto. With the denial of its Motion for
Reconsideration on January 26, 2000, petitioner now comes to this Court with
the instant petition arguing that the Court of Appeals gravely erred:
(a) When it refused to hold that the second Negotiated Contract of November 8, 1990 is null and void ab initio, notwithstanding that the execution thereof was in violation of Secs. 85, 86 and 87 of the Auditing Code of the Philippines (PD 1445) and LOI 968.
(b) When it refused to categorically hold that the said Negotiated Contract of November 8, 1990 required the prior approval of the City Council, notwithstanding the fact that the said contract would require the expenditure of public funds in the amount of P18,817,920.00 for one-year dumping operation, or the total amount of P94,089,600.00 for five years, and that it is the City Council that is vested by the Local Government Code (BP Blg. 337) with the power to appropriate city funds to cover expenses of the City Government.
(c) When it held that Petitioner started to dump garbage at the dumpsite and paid for such service, despite the fact that Respondent’s evidence proved otherwise; furthermore, the Court of Appeals failed to cite any specific evidence to support said conclusions of fact.
(d) When it held that the said Negotiated Contract of November 8, 1990 was ratified by the Petitioner by the aforesaid initial dumping of garbage and payment of services, overlooking the elementary doctrine that a void contract cannot be ratified.
(e) When it wrongly applied an Executive Order and administrative resolution as the applicable law to govern the aforesaid contract, notwithstanding that the Auditing Code of the Philippines (PD 1445) and the Local Government Code (BP 337) then had not been repealed by any legislative enactment, nor could the said executive issuances repeal them.
(f) When it held that the equities of the case should lean in favor of the respondent and thus failed to apply the doctrine that Government is not estopped to question the illegal acts of its officials.
(g) When it wrongly applied
the Imus case, not the Osmeña case, to the present case.[9]
Petitioner’s
remonstrations can be reduced to two (2) essential arguments:
First. That the second negotiated contract is null and void ab initio because its execution was done in violation of existing laws, more particularly Sections 85, 86 and 87 of Presidential Decree No. 1445 (otherwise known as the Auditing Code of the Philippines) and Section 177 (b) of Batas Pambansa Blg. 337 (also known as the Local Government Code of 1983); and
Second. That the facts and evidence do not support the Court of Appeals’ conclusion that, notwithstanding the lack of appropriation, subsequent acts of the petitioner constituted a ratification of the subject negotiated contract.
The issue of whether or
not the subject negotiated contract is null and void ab initio will be
discussed first.
Petitioner insists that
the subject contract failed to comply with the mandatory requirements of
Presidential Decree No. 1445, otherwise known as the Auditing Code of the
Philippines.
Section 85 thereof
provides:
Section 85. Appropriation before entering into contract. – (1) No contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor, the unexpected balance of which, free of other obligations, is sufficient to cover the proposed expenditure; (2) Notwithstanding this provision, contracts for the procurement of supplies and materials to be carried in stock may be entered into under regulations of the Commission provided that when issued, the supplies and materials shall be charged to the proper appropriation account. (Underscoring ours)
Section 86 of PD 1445
also provides as follows:
Section 86. Certificate showing appropriation to meet contract. – Except in a case of a contract for personal service, for supplies for current consumption or to be carried in stock not exceeding the estimated consumption for three months, or banking transactions of government-owned or controlled banks, no contract involving the expenditure of public funds by any government agency shall be entered into or authorized unless the proper accounting official or the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for the purpose and that the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof, subject to verification by the auditor concerned. The certification signed by the proper accounting official and the auditor who verified it, shall be attached to and become an integral part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the obligation of the government agency concerned under the contract is fully extinguished. (Underscoring ours)
Petitioner stresses that
failure to comply with the requirements underlined in Sections 85 and 86 of PD
1445 rendered the subject contract void, invoking Section 87 of PD 1445 which
provides:
Section 87. Void contract and liability of officer. – Any contract entered into contrary to the requirements of the two immediately preceding sections shall be void, and the officer or officers entering into the contract shall be liable to the government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties.
Is a contract entered
into by the city mayor involving the expenditure of public funds by the local
government without prior appropriation by the city council valid and
binding? Petitioner insists that the
answer is in the negative, arguing that there is no escaping the stringent and
mandatory requirement of a prior appropriation, as well as a certification that
funds are available therefor.
If we are to limit our
disquisition to the cited provisions of Presidential Decree No. 1445, or the
Auditing Code of the Philippines, in conjunction with Section 177 (b) of Batas
Pambansa Blg. 337, or the Local Government Code of 1983, which empowered the Sangguniang
Panlungsod to “appropriate funds for expenses of the city government, and fix
the salaries of its officers and employees according to law,” there would be no
debate that prior appropriation by the city council and a certification that
funds are available therefor is indeed mandatorily required.
There is no denying that
Sections 85 and 86 of P.D. 1445 (Auditing Code of the Philippines) provide that
contracts involving expenditure of public funds:
1) can be entered into only when there is an appropriation therefor; and
2) must be certified by the proper accounting official/agency that funds have been duly appropriated for the purpose, which certification shall be attached to and become an integral part of the proposed contact.
However, the very same
Presidential Decree No. 1445, which is the cornerstone of petitioner’s
arguments, does not provide that the absence of an appropriation law ipso
facto makes a contract entered into by a local government unit null and
void. Section 84 of the statute specifically
provides:
Revenue funds shall not be paid out of any public treasury or depository except in pursuance of an appropriation law or other specific statutory authority. (Underscoring ours)
Consequently, public
funds may be disbursed not only pursuant to an appropriation law, but also in
pursuance of other specific statutory authority, i.e., Section 84 of PD
1445. Thus, when a contract is entered
into by a city mayor pursuant to specific statutory authority, the law, i.e.,
PD 1445 allows the disbursement of funds from any public treasury or depository
therefor. It can thus be plainly seen
that the law invoked by petitioner Quezon City itself provides that an
appropriation law is not the only authority upon which public funds shall be
disbursed.
Furthermore, then Mayor
Brigido Simon, Jr. did not enter into the subject contract without legal
authority. The Local Government Code of
1983, or B.P. Blg. 337, which was then in force, specifically and exclusively
empowered the city mayor to “represent the city in its business transactions,
and sign all warrants drawn on the city treasury and all bonds, contracts and
obligations of the city.”[10] Such power granted
to the city mayor by B.P. Blg. 337 was not qualified nor restricted by any
prior action or authority of the city council.
We note that while the subsequent Local Government Code of 1991,[11] which took effect
after the execution of the subject contracts, provides that the mayor’s
representation must be “upon authority of the sangguniang panlungsod or pursuant
to law or ordinance,”[12] there was no such
qualification under the old code.
We must differentiate the
provisions of the old Local Government Code of 1983, B.P. Blg. 337, which was
then in force, from that of the Local Government Code of 1991, R.A. No. 7160,
which now requires that the mayor’s representation of the city in its business
transactions must be “upon authority of the sangguniang panlungsod or pursuant
to law or ordinance” (Section 455 [vi]).
No such prior authority was required under B.P. Blg. 337. This restriction, therefore, cannot be
imposed on the city mayor then since the two contracts were entered into before
R.A. No. 7160 was even enacted.
Under B.P. Blg. 337,
while the city mayor has no power to appropriate funds to support the contracts,
neither does said law prohibit him from entering into contracts unless and
until funds are appropriated therefor.
In fact, it is his bounden duty to so represent the city in all its
business transactions. On the other
hand, the city council must provide for the “depositing, leaving or throwing of
garbage”[13] and to appropriate
funds for such expenses.[14] (Section 177
[b]). It cannot refuse to so provide
and appropriate public funds for such services which are very vital to the
maintenance of cleanliness of the city and the good health of its inhabitants.
By entering into the two
contracts, Mayor Simon did not usurp the city council’s power to provide for
the proper disposal of garbage and to appropriate funds therefor. The execution of contracts to address such a
need is his statutory duty, just as it is the city council’s duty to provide
for said services. There is no
provision in B.P. Blg. 337, however, that prohibits the city mayor from
entering into contracts for the public welfare, unless and until there is prior
authority from the city council. This
requirement was imposed much later by R.A. No. 7160, long after the contracts
had already been executed and implemented.
Even the very Charter of
Quezon City,[15] more particularly
Section 9(f), Section 12(a) and Section 12(m) thereof, simply provide that the
mayor shall exercise general powers and duties, such as signing “all warrants
drawn on the city treasurer and all bonds, contracts, and obligations of the
city,”[16] even as it grants
the City Council the power, by ordinance or resolution, “to make all
appropriations for the expenses of the government of the city,”[17] as well as “to
prohibit the throwing or depositing of offal, garbage, refuse, or other
offensive matter in the same, and to provide for its collection and disposition
x x x.”[18]
While the powers and
duties of the Mayor and the City Council are clearly delineated, there is
nothing in the cited provisions, nor even in the statute itself, that requires
“prior authorization by the city council by proper enactment of an ordinance”
before the City Mayor can enter into contracts.
Private respondent Lexber
asserts that the subject contract was entered into by Mayor Simon in behalf of
the Quezon City government pursuant to specific statutory authority, more
particularly the provisions of Executive Order No. 392. In accordance with Article XVIII, Section 8
of the 1987 Constitution, then President Corazon C. Aquino issued E.O. No. 392
constituting the Metropolitan Manila Authority (or MMA) to be composed of the
heads of the four (4) cities and thirteen (13) municipalities comprising the
Metropolitan Manila area. The said
Executive Order empowered the MMA to “have jurisdiction over the delivery of
basic urban services requiring coordination” in the Metropolitan area,
including “sanitation and waste management.”[19]
To fulfill this mandate,
the MMA, through Resolution No. 17, Series of 1990, resolved that pursuant to
Section 2 of E.O. No. 392, the:
x x x LGUs remitting their contributions to the MMA within the prescribed period shall be entitled to a financial assistance in an amount equivalent to 20% of their remittances provided that the amount is used exclusively to augment the effective delivery of basic urban services requiring coordination.
The Metropolitan Manila
Council (or MMC) also issued Resolution No. 15, Series of 1991, authorizing the
Chairman of the MMC to enter into a memorandum of agreement or (MOA) with any
local chief executive in Metropolitan Manila for the purpose of managing
garbage collection and disposal, among other basic urban services. Taking their cue from Executive Order No.
392 and the pertinent resolutions of the MMA and MMC, the then Mayors of Quezon
City and the Municipality of Antipolo entered into a tripartite MOA with
respondent Lexber, towards the establishment of the proposed Quezon City
Landfill Disposal System.
It is true that the first
negotiated contract between Mayor Simon, Jr. and respondent Lexber, which
provided for the necessary infrastructure of the dumpsite, was executed without
prior authority or appropriation by the city council. Nevertheless, recognizing the necessity, if not the urgency, of
the project, petitioner honored the said contract and paid respondent Lexber
the contract price of P4,381,069.00.[20]
Respondent Lexber avers
that immediately following the completion of the project in December 1991,
petitioner in fact availed of the facilities by delivering and dumping garbage
at the site in accordance with the stipulations in the second negotiated
contract. And yet, after having spent
millions of public funds to build the necessary infrastructure, as well as for
site development of the sanitary landfill, petitioner, under the
newly-installed administration of Mayor Ismael Mathay, Jr., refused to honor
the second negotiated contract by: (1)
discontinuing the city’s use of the sanitary landfill; (2) refusing to pay
respondent Lexber for services already rendered from December of 1991 to May of
1992; and (3) denying any liability under the second negotiated contract, on
the grounds that the same was without prior authority of the city council, and
that it was neither approved nor ratified by the said body. Moreover, Mayor Mathay, Jr. refused to pay
its obligation to respondent Lexber since no provision therefor was made in the
1992/1993 annual city budget.
The trial court ruled
that while there may not have been prior authority or appropriation to enter
into and implement the second negotiated contract, the project denominated as
“Quezon City Landfill Disposal System” was duly supported by a Certificate of
Availability of Funds dated April 4, 1991 signed by the Quezon City Auditor,
Reynaldo P. Ventura, and Treasurer, Montano L. Diaz, stating as follows:
Pursuant to the provisions of Section 86 of P.D. No. 1445, LOI 968
and Section 46 of P.D. No. 177, I hereby certify that funds have been duly
appropriated and alloted under Advice of Allotment No. 1 and 2 dated March 31,
1991 and in the total amount of P2,620,169.00; P11,783,399.00 covering the
contract entered into with Lexber, Inc. with business address at 65 Panay
Avenue, Quezon City said amount is available for expenditure on account
thereof.[21]
The existence of said
document led the trial court to conclude thus:
However, a close examination of the Certificate of Availability of Funds dated December 3, 1990 shows that the appropriated amounts of P1,700,000.00, 2,641,922.00, and P40,000.00 totaled P4,381,922.00 and not P4,341,922.00, which amount is, in fact, P853.00 more than the contract price of Negotiated Contract dated September 10, 1990. This only shows that as of April 4, 1991, there was sufficient appropriation to cover at least for a period of three (3) months, in order to comply with the provisions of Section 86 of PD 1445. Moreover, any payment made will comply with the provision of Section 84 of PD 1445 which states that: “Revenue funds shall not be paid out of any public treasury or depository except in pursuance of an appropriation law or other specific statutory authority.”
In any case, the defendant city can easily make available the necessary funds at the beginning of the year in the general appropriation to cover the probable expenses which it would have to incur, considering that pursuant to Resolution No, 72, Series of 1990 of the Metropolitan Manila Authority, the Local Government Units are entitled to a financial assistance in an amount equivalent to 20% of their remittances provided that the amount is used exclusively to augment the effective delivery of basic services requiring coordination. In fact, the amount of FIVE MILLION PESOS (P5,000,000.00) has already been set aside in order to be available to augment garbage collection and disposal in Quezon City.
It must be noted that the Negotiated Contract dated November 8,
1990 is not ipso facto absolutely null and void. The subject thereof is perfectly within the
authority of the city government. It is
pursuant to the Tripartite Agreement entered into between the plaintiff, the
defendant, and the Municipality of Antipolo.
The plaintiff was given the exclusive right to exercise acts stated in
the two negotiated contracts, which are entered into to further carry out and
implement the provisions of the Tripartite Agreement.[22]
The Court of Appeals
affirmed the trial court’s findings that the second negotiated contract was
executed by virtue of a specific statutory authority, or pursuant to law,
holding that:
Executive Order No. 392 (constituting the Metropolitan Manila Authority, providing for its powers and functions and for other purposes) and pertinent Resolution No. 72, Series of 1990 of MMA, and Resolution No. 15, Series of 1991 of MMC, find application and therefore should govern the subject transactions.
Worthy to stress at this point is the fact that pursuant to Sec. 1, E.O. 392, the then Metropolitan Manila Authority was tasked, among others, with the delivery of basic services in the Metropolitan Area, whose services include garbage collection and disposal. To carry out this mandate and effectively deliver other basic urban services requiring coordination of local government units, the Metropolitan Manila Authority through its Resolution No. 72, Series of 1990, granted financial assistance to all local government units (LGUs) comprising Metropolitan Manila in an amount equivalent to 20% of their remittances as provided under E.O. 392. Likewise, the Metropolitan Manila Council, in its Resolution No. 15, Series of 1991, resolved to authorize the Chairman of the MMC to enter into memorandum of Agreement (MOA) with the Local Chief Executives in Metro Manila for the purpose of, among other things, the management of garbage collection and its disposal.
The foregoing authorities therefore fully clothed Mayor Brigido
Simon, Jr. with the authority to enter and sign the subject contract for and in
behalf of the city government even without express authority from the City
Council.[23]
While it is true that the
MMA has no legislative power, E.O. No. 392 specifically empowered the MMA to
“have jurisdiction over the delivery of basic urban services requiring coordination,”
such as “sanitation and waste management.”[24] Said E.O. did not
repeal pertinent provisions of B.P. 337, but specifically exempts the MMA from
the application of E.O. 392[25] (Section 11 of E.O
392). There is no conflict as well with
the provisions of P.D. No. 1445 because Sec. 84 thereof also recognizes
appropriation by “other statutory authority.”
E.O. 392 and MMA
Resolutions Nos. 72 and 15 allowed for direct coordination between the MMA and
the covered local government units to expedite the effective delivery of basic
services requiring coordination, such as collection and disposal of
garbage. To this end, the MMA
Resolutions (series of 1990) granted financial assistance to all covered local
government units in an amount equivalent to 20% of their remittances to fund
the delivery of said services, pursuant to the provisions of Sec. 7 of E.O. No.
392:
“x x x city and municipal treasurers of the local government units comprising Metropolitan Manila shall continue to collect all revenues and receipts accruing to the Metropolitan Manila Commission and remit the same to the Authority; Provided that such income collections as well as the share of the authority from the regular sources of revenue in the General Fund of the city or municipality as local counterpart for the integrated basic services and developmental projects shall be treated as a trust fund in their account. Provided further that the remittance thereof shall be effected within the first thirty (30) days following the end of each month. x x x”
There was, thus, no
justifiable reason for petitioner not to allocate or appropriate funds at the
start of each fiscal year considering that a trust fund had been established to
pay for “the effective delivery of basic urban services requiring coordination,”
foremost of which is the collection and disposal of garbage.
LOI No. 968, signed by
then President Marcos on December 17, 1979, also provides in part that “all
contracts for capital projects and for supply of commodities and services,
including equipment, maintenance contracts, and other agreements requiring
payment which are chargeable to agency current operating on capital expenditure
funds, shall be signed by agency heads or other duly authorized official only
when there are available funds. The chief
accountant of the contracting agency shall sign such contracts as witness and
contracts without such witness shall be considered as null and void.”
However, this requirement
does not apply to contracts executed by local chief executives since the said LOI
No. 968 was directed only to “Ministries and Heads/Chief Accountants of
Ministry, Bureau, Office, Agency of the National Government, including State
Universities and Colleges, and the Chairman, Commission on Audit.” Quezon City,
or any urbanized city for that matter, cannot be considered a ministry, bureau,
office or agency of the national government; neither is the city mayor a
minister or head of a ministry, bureau, office or agency of the national
government. Hence, the mayor of Quezon
City is not covered by LOI No. 968. The
prevailing law in this particular instance is the Local Government Code of 1983
or B.P. Blg. 337.
Therefore, we find no
cogent reason to disturb the conclusions of the trial court as affirmed by the
Court of Appeals in this regard. It is
clear that the second negotiated contract was entered into by Mayor Brigido
Simon, Jr. pursuant to law or specific statutory authority as required by P.D.
No. 1445.
There is also no merit in
petitioner’s claim that there was no appropriation therefor, for it is evident
that even as early as April 4, 1991, funds which were certified to as available
had been allocated for use in the first few months operation of the sanitary
landfill. The problem arose only because
the new administration unjustifiably refused to abide by the stipulations in
the second negotiated contract. Hence,
petitioner’s arguments on this issue fail to convince this Court that the
second negotiated contract was null and void ab initio for lack of prior
appropriation or authority on the part of Mayor Brigido Simon, Jr.
It is of no moment that
the certificate referred to by the trial court did not state “that the amount
necessary to cover the proposed contract for the current fiscal year is
available for expenditure on account thereof.”[26] The Certificate of
Availability of Funds,[27] though dated
December 3, 1990, merely showed that funds for the Landfill Disposal System was
available. Even if the surplus amount
was just sufficient to cover at least three (3) months of operations as of
April 4, 1991, said monthly payments were not due yet as the infrastructure was
still being completed. The project was
completed in December of 1991 and dumping was to commence only thereafter. Thus, the funds to cover the 1992 fiscal
year could have been made available and appropriated therefor at the beginning
of said year. That the Quezon City
government later refused to appropriate and approve payments to respondent
Lexber under the contract despite its use of the facilities for several months
in 1992, is not respondent’s fault, and being the aggrieved party, it cannot be
made to suffer the damage wrought by the petitioner’s failure or refusal to
abide by the contract.
On the issue of
subsequent ratification by petitioner, the Court of Appeals held:
Granting but without conceding that Mayor Brigido Simon, Jr. needs
to secure prior authorization from the City Council for the enforceability of
the contracts entered into in the name of the City government, which he failed
to do according to the appellant, We believe that such will not affect the
enforceability of the contract because of the subsequent ratification made by
the City government. Thus, when
appellant City government, after the construction by the appellee of the
dumpsite structure in accordance with the contract plans and specifications,
started to dump garbage collected in the City and consequently paid the
appellee for the services rendered, such acts produce and constitute a
ratification and approval of the negotiated contract and necessarily should
imply its waiver of the right to assail the contract’s enforceability.[28]
We are not dissuaded by
petitioner’s arguments that there can be no ratification due to the absence of
an explicit or tacit approval of the second negotiated contract. At the outset, the issue raised by
petitioner that the subject contract is null and void ab initio, and
therefore not capable of ratification, has been laid to rest by the inevitable
conclusion that the said contract is valid and binding. Consequently, ratification of the subject
contract is not necessary.
Be that as it may, it
cannot be denied that there was constructive ratification on the part of
petitioner. The records show that upon
completion of the infrastructure and other facilities, petitioner, albeit
still under the administration of Mayor Brigido Simon, Jr., started to dump
garbage in the premises. In fact, on
December 11, 1991, a Notice to Commence Work,[29] implementing the contract for the maintenance of the
sanitary landfill starting December 15, 1991 to December 31, 1995, was issued
by said Mayor, as recommended by Project Manager Rene R. Lazaro and City
Engineer Alfredo Macapugay.
The records also reveal
that petitioner issued Disbursement Vouchers[30] of various amounts covering the period between March
1, 1992 to April 30, 1992 for the services rendered by the Mud Regal Group,
Incorporated to haul garbage to the sanitary landfill. The said disbursement vouchers were passed
in audit and duly approved and paid by petitioner. These are facts and circumstances on record which led the trial
court, the appellate court, and this Court to
affirm the conclusion that petitioner had actually ratified the subject
contract.[31]
Also part of the evidence
on record are receipts of various amounts paid by respondent Lexber to Mud
Regal Group, Inc. for the supply of earth moving equipment used by Lexber to
maintain the sanitary landfill covering the period from December 1991 to August
1992.[32] There is also a
collection letter from Mud Regal Group, Inc. addressed to respondent Lexber for
unpaid bills covering the period from September to December 1992.[33] While
corresponding vouchers were prepared by petitioner to pay respondent Lexber for
work accomplished by the latter in the maintenance of the sanitary landfill for
the period spanning December 1991 to June 1992,[34] these were never
processed and approved for payment since action thereon was overtaken by the
change in leadership of the city government.
By then, the new dispensation had already discontinued using the sanitary
landfill for reasons it did not make known to respondent Lexber.
It is evident that
petitioner dealt unfairly with respondent Lexber. By the mere pretext that the subject contract was not approved
nor ratified by the city council, petitioner refused to perform its obligations
under the subject contract. Verily, the
same was entered into pursuant to law or specific statutory authority, funds
therefor were initially available and allocated, and petitioner used the
sanitary landfill for several months. The present leadership cannot unilaterally decide to disregard the
subject contract to the detriment of respondent Lexber.
The mere fact that
petitioner later refused to continue dumping garbage on the sanitary landfill
does not necessarily prove that it did not benefit at the expense of respondent
Lexber. Whether or not garbage was
actually dumped is of no moment, for respondent Lexber’s undertaking was to
make available to petitioner the landfill site and to provide the manpower and
machinery to maintain the facility.
Petitioner, by refusing to abide by its obligations as stipulated in the
subject negotiated contract, should be held liable to respondent Lexber in
accordance with the terms of the subject contract.
Petitioner’s refusal to
abide by its commitments gave rise to an untenable situation wherein petitioner
effectively denied the existence and validity of the subject contract even
while respondent Lexber was still bound by it.
This situation is inconsistent with the principle that obligations arising
from contracts have the force of law between the contracting parties and each
party is bound to fulfill what has been expressly stipulated therein.[35] Only respondent Lexber was bound by the contract
while petitioner acted as if it were free therefrom.[36] The Court of Appeals held that:
Moreover, the contention of appellant, if sustained, will undeniably result in grave injustice and inequity to appellate Lexber, Inc. The records will reveal that appellee never solicited upon the City government to utilize its properties for a landfill site, as appellee originally conceived of devoting its property to a more viable undertaking, bamboo plantation in partnership with foreign firm. On the other hand, it was the City government, then beset with serious garbage problem that enticed and convinced Lexber, Inc. to offer its properties as a landfill site, with the assurance of the opportunities contained in the tri-partite agreement. When appellee acceded to their request, three contracts unilaterally prepared by the City government was presented to him, the terms and conditions of which were all established and prescribed by appellant, and appellee’s mere participation in the contract’s perfection was simply the affixing of his signature therein.
Clearly, the equities of the case are with appellee Lexber, Inc. Even fair dealing alone would have required the appellant to abide by its representations, which it did in the inception, but was later dishonored by the new administration of Mayor Mathay, Jr. Appellee faithfully performed its undertakings set forth in the contract, upon the appellant’s assurance that sufficient funds shall come from the city’s statutory contribution to the MMA. Had it not (sic) for the said assurance, Lexber, Inc. for sure, would not have ventured into such costly business undertaking. No one in his right frame of mind would have entered into such kind of contract and invest his fortune unless assured of the availability of funds to compensate its financial investment.
As correctly pointed out by the court a quo, appellant
having taken advantage of and benefited from the appellee through the assailed
negotiated contract shall not be permitted to attack it on the ground that the
contract did not bear the necessary approval.[37]
Finally, we come to the
issue raised by petitioner that the Court of Appeals gravely erred in holding
that the Imus case, not the Osmeña case, is applicable to the
instant controversy. We note that the
Court of Appeals did not discuss either case but merely adopted the exhaustive
discussion of the trial court on the matter.
Before the court a quo, herein respondent Lexber relied on the
ruling of this Court in the case of Imus Electric Company v. Municipality of
Imus,[38] wherein this Court ruled:
The defendants contend that the contract in question is null and void on the ground that the former municipal council of Imus approved it without having the necessary funds to pay for the value of the service to be rendered by the plaintiff for a period of ten (10) years, which amounted to P24,300, and without the provincial treasurer’s previous certificate to the effect that said funds have been appropriated and were available, in violation of the provisions of sections 606, 607 and 608 of the Regional Administrative Code of 1917. The above-cited legal provisions read as follows:
SEC. 606. Appropriation antecedent to making of contract. – No contract involving the expenditure of public funds shall be made until there is an appropriation therefor, the unexpended balance of which, free of other obligations, is sufficient to cover the proposed expenditure. This provision shall not, however, be construed to prevent the purchasing and carrying of supplies in stock, under the regulations of the Bureau of Audits, provided that when issued such supplies shall be charged to the proper appropriation account.
SEC. 607. Certificate showing appropriation to meet contract. – Except in the case of a contract for personal service or for supplies to be carried in stock, no contract involving an expenditure by the Insular Government of three thousand pesos or more shall be entered into or authorized until the Insular Auditor shall have certified to the officer entering into such obligation that funds have been duly appropriated for such purpose and that the amount necessary to cover the proposed contract is available for expenditure on account thereof. When application is made to the Insular Auditor for the certificate herein required, a copy of the proposed contract or agreement shall be submitted to him accompanied by a statement in writing from the officer making the application showing all obligations not yet presented for audit which have been incurred against the appropriation to which the contract in question would be chargeable; and such certificate, when signed by the Auditor, shall be attached to and become a part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the Government is discharged from the contract in question.
Except in the case of a contract for supplies to be carried in stock, no contract involving the expenditure by any province, municipality, township, or settlement of two thousand pesos or more shall be entered into or authorized until the treasurer of the political division concerned shall have certified to the officer entering into such contract that funds have been duly appropriated for such purpose and that the amount necessary to cover the proposed contract is available for expenditure on account thereof. Such certificate, when signed by the said treasurer, shall be attached to and become a part of the proposed contract and the sum so certified shall not thereafter be available for expenditure for any other purpose until the contract in question is lawfully abrogated or discharged.
For the purpose of making the certificate hereinabove required ninety per centum of the estimated revenues and receipts which should accrue during the current fiscal year, but which are yet uncollected, shall be deemed to be in the treasury of the particular branch of the Government against which the obligation in question would create a charge.
SEC. 608. Void contract; Liability of officer. – A purported contract entered into contrary to the requirements of the next preceding section hereof shall be wholly void, and the officer assuming to make such contract shall be liable to the Government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties. (Underscoring ours)
The defendants contend that the additional appropriation made by the then municipal council was inadequate on the ground that it was the duty of the latter to appropriate funds for the whole terms of the contract and that the contract in question falls within the prohibition of section 608 because in reality there was no appropriation for the sum of P24,300, nor did the provincial treasurer certify that such appropriation was made and that the funds for the same were available. (Underscoring ours)
The inconsistency of the defendants’ claim becomes obvious merely by taking into consideration that the contract entered into by the parties was for the sale of electric current at the rate of P4.50 monthly for every lamp or light of 50 watts, or the sum of P202.50 every month. Under this agreement, the municipality of Imus was not bound, nor is it bound, to pay the price of the electric current until the same has been furnished, and inasmuch as the period of one month was made the basis thereof, there is no doubt but that neither is the said municipality obliged to pay for the current except at the end of every month. It is true that the duration of the contract was fixed at ten (10) years, a period which was accepted by the municipality on the ground that only under the terms of the contract and the law, the municipality was not bound to make advanced payments and, consequently, there was no reason for it to appropriate funds for the said public service except for a period of one month or one year, at most, if it had sufficient funds, in order to comply with the provisions of section 2296 of the Revised Administrative Code, which requires that municipalities should, at the beginning of every year, make a general appropriation containing the probable expenses which, they would have to incur. (Emphasis supplied)
Petitioner, on the other
hand, argued that the above-quoted ruling is no longer applicable, citing this
Court’s ruling in the more recent case of Osmeña v. Commission on Audit,[39] to wit:
The Auditing Code of the Philippines (P.D. 1445) further provides that no contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor and the proper accounting official of the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for the purpose and the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof. Any contract entered into contrary to the foregoing requirements shall be VOID.
Clearly then, the contract entered into by the former Mayor Duterte was void from the very beginning since the agreed cost for the project (P8,368,920.00) was way beyond the appropriated amount (P5,419,180.00) as certified by the City Treasurer. Hence, the contract was properly declared void and unenforceable in COA’s 2nd Indorsement, dated September 4, 1986. The COA declared and we agree, that:
The prohibition contained in Sec. 85 of PD 1445 (Government Auditing Code) is explicit and mandatory. Fund availability is, as it has always been, an indispensable prerequisite to the execution of any government contract involving the expenditure of public funds by all government agencies at all levels. Such contracts are not to be as final and binding unless a certification as to the funds availability is issued (Letter of Instruction No. 767, s. 1978). Antecedent advance appropriation is thus essential to government liability on contracts. This contract being violative of the legal requirement aforequoted, the same contravenes Sec. 85 of PD 1445 and is null and void by virtue of Sec. 87.
The trial court, which
was affirmed by the Court of Appeals, concluded that:
The contention of defendant that the Imus case is no longer applicable in view of the explicit provisions of PD 1445 is without merit. The prohibitions expressed in Sections 85, 86, and 87 of PD 1445 are already embodied in the provision of Revised Administrative Code, specifically Sections 606, 607 and 608, yet, the Supreme Court treated the contract therein as valid and required the defendant municipality to comply with its obligation despite the absence of prior approved appropriation at the time of the execution of the contract. The reason is that the obligation is not payable until the performance of the services contracted. That is the difference between the “Imus case” and the “Osmeña case.”
In the former, the obligation to be rendered is the furnishing or sale of electric current which the defendant municipality is not bound to pay until the same has been furnished.
While in the latter, the contract is for the construction of a modern abattoir. The amount payable is already fixed at the time the contract was executed. Moreover, what made the Supreme Court declare the contract entered therein as invalid is the attainment of the finality of the findings of the Commission on Audit, which the petitioner mayor previously invoked.
Thus, the Highest Tribunal said, and this Court quotes:
As a matter of fact, the City of Cebu relied on the above pronouncement and interposed the same as its affirmative defense, so much so that petitioner cannot now assert that it was void having been issued in excess of COA’s jurisdiction. A party cannot invoke the jurisdiction of a court or an administrative body to secure affirmative relief against his opponent and after obtaining or failing to obtain such relief, repudiate or question that same jurisdiction. It is not right for a party who has affirmed and invoked the jurisdiction of a court in a particular matter to secure an affirmative relief, to afterwards deny the same jurisdiction to escape a penalty.
Besides, neither the petitioner nor HFCCI questioned the ruling of
COA declaring the invalidity of the abattoir contract, thereby resulting in its
finality even before the civil case was instituted. Petitioner could have brought the case to the Supreme Court on a
petition for certiorari within thirty days from receipt of a copy of the
COA decision in the manner provided by law and the Rules of Court. A decision of the Commission or any of its
Auditor not appealed within the period provided by law, shall be final and
executory.[40]
Contrary to petitioner’s
arguments, the facts in the Osmeña case are not parallel to the facts in
the instant case. While in the former
the construction of an abattoir entailed the payment in full of a fixed amount,
the case at bar involved a contract for services still to be rendered which was
payable on a monthly basis, just as in the Imus case. In the latter case, the Supreme Court did
not declare the contract null and void ab initio for the reason that
appropriation for the project can be made subsequent to the execution of the
contract. Consequently, the ruling in
the Imus case is germane to the instant case. Furthermore, the trial court noted that while herein petitioner
would attack the subject contract for being fatally defective, the Commission
on Audit did not declare the said contract as null and void, unlike in the Osmeña
case where the questioned contract was declared invalid by the COA. Hence, the ruling in the Osmeña case
finds no application in the instant controversy.
While the contracts were
admittedly negotiated contracts, this fact was never raised by the petitioner
before the trial court, Court of Appeals, and in the instant petition. The question of the validity of the said
contracts never hinged on the fact that there was no public bidding. What is on record is that it was Mayor Simon
who initiated the negotiations to convince respondent to allow the use of its
property as a dumpsite.
Public bidding may have
been dispensed with, not only because “time is of the essence” but in
recognition of the reality that offering property to be used as a dumpsite is
not an attractive nor lucrative option for property owners. This reality is all the more glaring in the
current situation where Metro Manila local government units are seemingly
unable to cope with the disastrous lack of garbage dumping sites. A major part of the problem is that no one
wants to be the dumping ground of someone else’s garbage. This problem is compounded by recent events
where tragedy has befallen scavengers and residents in a Quezon City dumpsite
that should have been closed years ago.
It would no longer be prophetic to say that had Quezon City used the
subject dumpsite and discontinued the use of the Payatas dumpsite way back in
1991, tragedy therein would have been averted.
Finally, petitioner’s
refusal to honor the contract is not only contrary to law, but also grossly
unfair to respondent Lexber. It was
petitioner that first offered and later persuaded respondent Lexber to convert
the latter’s property into a sanitary landfill for petitioner’s exclusive
use. While the property could have been
used for other more lucrative and pleasant purposes, petitioner convinced
respondent Lexber by its assurances and stipulations in the contract. In turn, respondent Lexber relied on
petitioner to abide by their contract, only to be rebuffed after petitioner had
already taken initial advantage of the facilities. By virtue of the infrastructure intended for the sanitary
landfill that was erected thereon, respondent Lexber could not divert its use
to other purposes. It is but fair that respondent
Lexber be compensated for the financial losses it has incurred in accordance
with the obligation of petitioner as stipulated in the second negotiated
contract.
WHEREFORE, in view of all the foregoing, the Decision
of the Court of Appeals in CA-G.R. CV No. 59541 affirming the judgment of the
Regional Trial Court of Quezon City, Branch 220 in Civil Case No. Q-94-19405 is
hereby AFFIRMED in toto. The
instant petition for review is DENIED for lack of merit.
No costs.
SO ORDERED.
Davide, Jr., C.J. (Chairman),
Puno, and Kapunan, JJ., concur.
Pardo,
J., dissent. See attached.
[1] Penned
by Associate Justice Omar U. Amin and concurred in by Associate Justices Hector
L. Hofileña and Jose L. Sabio, Jr.; Petition, Annex “A”; Rollo, pp.
51-59.
[2] Penned
by Judge Prudencio Altre Castillo, Jr.; Records, pp. 321-333.
[3] Exhibit
“D”; Records, pp. 11-13.
[4] Covered
by Transfer Certificate of Title No. 225924 of the Register of Deeds for
Marikina, Metro Manila in the name of respondent; Exhibit “A”, Records, p. 127.
[5] Exhibit
“E”; Records, pp. 14-18.
[6] Exhibit
“I”; Records, pp. 20-26.
[7] See
Exhibit “J”; Records, p. 133.
[8] Judgment,
Civil Case No. Q-94-19405, p. 13; Records, p. 333.
[9] Petition,
pp. 18-19; Rollo, pp. 19-20.
[10] Section
171 (2)(g), B.P. Blg. 337.
[11] Republic
Act No. 7160.
[12] Section
455 (vi), R.A. No. 7160.
[13] B.P.
Blg. 337, Section 177(j).
[14] B.P.
Blg. 337, Section 177(b).
[15] Commonwealth
Act No. 502.
[16] Section
9(f).
[17] Section
12(a).
[18] Section
12(m).
[19] Section
1, Executive Order 392.
[20] Exhs.
“H” and “H-1”; Records, pp. 131-132.
[21] Exhs.
“Z” and “3”; Records, p. 261.
[22] RTC
Decision, Rollo, p. 114.
[23] CA
Decision, Rollo, p. 58.
[24] Section
1, E.O. 392.
[25] Section
11, E.O. 392.
[26] Section
86, P.D. 1445.
[27] Exhs.
“Z” and “3”, Records, p. 261.
[28] CA
Decision, Rollo, p. 56.
[29] Exhibit
“J”; Records, p. 133.
[30] Exhibits
“K”, “K-1”, “K-2” and “K-3”; Records, pp. 134-137.
[31] Bisaya
Land Transportation Co., Inc. v. Sanchez, 153 SCRA 532, 541 (1987).
[32] Exhibits
“L” to “L-17” (Inclusive); Records, pp. 138-146.
[33] Exhibit
“M”; Record, p. 147.
[34] Exhibits
“N”, “N-1-A”, “N-1-B”, “N-2”, “N-2-A”, “N-2-B”, “N-3”, “N-3-A”, “N-3-B”, “N-4”,
“N-4-A”, “N-5”, “N-5-A”, “N-6”, and “N-6-A”; Records, pp. 150-163.
[35] Barons
Marketing Corp. v. CA, 28 SCRA 96, 106 (1998).
[36] Cf.:
Allied Banking Corp. v. CA, 284 SCRA 357, 364 (1998).
[37] Court
of Appeals Decision, Rollo, pp. 56-57.
[38] 59
Phil. 823 (1934).
[39] 230
SCRA 585 (1994).
[40] RTC
Decision, Rollo, pp. 111-112.