SECOND DIVISION
[G.R. No. 135657. January 17, 2001]
JOSE V. LAGON, petitioner, vs. HOOVEN COMALCO
INDUSTRIES, INC., respondent.
D E C I S I O N
BELLOSILLO, J.:
This petition for review
on certiorari seeks to set aside the Decision of the Court of Appeals of
28 April 1997 which in turn set aside the decision of the Regional Trial Court
of Davao City and ordered petitioner Jose V. Lagon to pay respondent Hooven Comalco
Industries, Inc. (HOOVEN) the amount of P69,329.00 with interest at
twelve percent (12%) per annum computed from the filing of the complaint until
fully paid, plus attorney’s fees and costs,[1] as well as the Resolution of the appellate
court denying reconsideration thereof.[2]
Petitioner Jose V. Lagon
is a businessman and owner of a commercial building in Tacurong, Sultan
Kudarat. Respondent HOOVEN on the other
hand is a domestic corporation known to be the biggest manufacturer and
installer of aluminum materials in the country with branch office at E. Quirino
Avenue, Davao City.
Sometime in April 1981
Lagon and HOOVEN entered into two (2) contracts, both denominated Proposal, whereby for a total consideration of P104,870.00
HOOVEN agreed to sell and install various aluminum materials in Lagon’s
commercial building in Tacurong, Sultan Kudarat.[3] Upon execution of the contracts, Lagon paid
HOOVEN P48,00.00 in advance.[4]
On 24 February 1987
respondent HOOVEN commenced an action for sum of money with damages and
attorney’s fees against petitioner Lagon before the Regional Trial Court of
Davao City. HOOVEN alleged in its
complaint that on different occasions, it delivered and installed several
construction materials in the commercial building of Lagon pursuant to their
contracts; that the total cost of the labor and materials amounted to P117,329.00
out of which P69,329.00 remained unpaid even after the completion of the
project; and, despite repeated demands, Lagon failed and refused to liquidate
his indebtedness. HOOVEN also prayed
for attorney’s fees and litigation expenses, and in support thereof, presented
its OIC, Alberto Villanueva, and its employee, Ernesto Argente, and other
witnesses, as well as several documentary evidence consisting mainly of the two
(2) proposals, invoices and delivery receipts.
Lagon, in his answer,
denied liability and averred that HOOVEN was the party guilty of breach of
contract by failing to deliver and install some of the materials specified in
the proposals; that as a consequence he was compelled to procure the
undelivered materials from other sources; that as regards the materials duly
delivered and installed by HOOVEN, they were fully paid. He counterclaimed for actual, moral,
exemplary, temperate and nominal damages, as well as for attorney’s fees and
expenses of litigation.
On 9 October 1987, upon
request of both parties, the trial court conducted an ocular inspection of
Lagon’s commercial building to determine whether the items alleged in the
complaint and appearing in the invoices and delivery receipts had been
delivered and installed on the premises.
The result of the ocular inspection was -
1) with respect to the items covered by Exhibit “A” and submarkings that there are only seventeen (17) light diffusers, 13 in the ceiling of the ground and 4 on the mezzanine (Ocular Inspection, TSN, pp. 5 to 6); 2) on Exhibit “B” and submarkings, there are only twenty-three (23) light aluminum boxes, 14 aluminum boxes in the ceiling of the mezzanine and 9 on the ceiling of the ground floor (Ocular Inspection, TSN, p. 7); 3) on Exhibit “C-1,” the items are missing in the area where they were supposed to be installed; 4) on Exhibit “C-2,” admitted by defendant Lagon when he stated that “I will admit that these were installed by the plaintiff but I do not know exactly the materials, but I really accept that these were installed sometime in 1981, before the occupation of the DBP. But I have paid that already in 1981. I could not identify the materials delivered in 1981 because I do not know the exact names of those materials.” (Ocular Inspection, TSN, p. 12); 5) on Exhibit “C-2,” the glasses are not tinted but plain white; on Exhibit “C-3,” the materials cannot be formed (sic) in the place where they are supposed to be (Ocular Inspection, TSN, p.7); 6) Exhibit “D” and “D-1,” that the materials were supplied by plaintiff but they did not install them. It was the defendant who caused the installation thereof (Ocular Inspection, TSN, p. 13.); and 7) Exhibit “E-1,” as NU- Main and Cross-Runners and supplied by plaintiff but plaintiff did not install. They had it installed (Ocular Inspection, TSN, p. 14).
In due course the trial
court rendered a decision partly on the basis of the result of the ocular
inspection finding that the total actual deliveries and installations made by
HOOVEN cost P87,140.00.
Deducting therefrom P48,000.00 which Lagon paid in advance upon
execution of their contracts with no further payments appearing to have been
made thereafter, only P39,140.00 remained unpaid and where Lagon
incurred in delay. The trial court also
awarded HOOVEN P3,255.00 as attorney’s fees, but sustained Lagon’s
counterclaims and awarded him P26,120.00 as actual damages representing
the value of the undelivered and uninstalled materials, and P30,000.00
as attorney’s fees in addition to litigation expenses of P45,534.50. According to the court a quo[5]–
As a result of the partial breach of contract on plaintiff's
(Hooven Comalco) part, the defendant is entitled to actual damages only to the
extent of the undelivered materials and undone labor or to the amount of P26,120.00. This P26,120.00 will be partially
offsetted (sic) to the P39,140.00 unpaid balance of the defendant
(Lagon), so that the difference that remain (sic) payable to plaintiff is P13,020.00. Evidence is insufficient to show that bad
faith existed in the filing of the instant complaint for collection against the
defendant. Plaintiff's obstinate
conduct in prosecuting its claim spending for litigation expenses and for its
lawyers negate the existence of bad faith.
The fact alone that the findings of fact show an unpaid account of the
defendant is proof that the complaint is not completely unfounded though
evidence shows also that plaintiff is guilty of partial breach of contract by
reason of failure to completely deliver and install the materials defendant
ordered pursuant to the contract so that plaintiff is liable for damages. As plaintiff acted in good faith in the
filing of the instant complaint in the belief that it has a valid cause of
action against the defendant to enforce its claim, engaging a lawyer to
prosecute it, plaintiff is entitled to a reasonable attorney’s fees equivalent
to 25% of the collectible amount of P13,020.00 or the amount of P3,225.00. Defendant's claim of attorney’s fees in the
amount of P152,629.15 is in the opinion of the court clearly
unreasonable and unconscionable considering the nature of the action and the
amount involved. The court has the
power to reduce it to render it reasonable and conscionable whether the
contract for attorney's fees is written or oral. The attorney’s fees is fixed at P30,000.00. The defendant presented evidence of
litigation expenses incurred in the course of the trial for plane fare of its
lawyer in coming to Davao City from Manila from 1987 up to July 1990 in the
total amount of P34,730.50 as evidenced by Exhibit “11” to “11-E.” The
records show that the defendant’s counsel came to Davao City from Manila to
attend eleven (11) hearings of the case and the plane fare from 1987 up to
August, 1989 is P2,524.50 and from August 1989 to June 1990 is P3,007.50. Hotel expenses of defendant’s counsel at the
Maguindanao Hotel where he was billeted everytime he came to Davao City to
attend the trial amounted to P11,824.00 as evidenced by Exhibit “17,”
the certification issued by the said hotel management. So that the total amount of the actual
damage suffered by defendant is P45,534.50. Said amount of P45,534.50 is partially offsetted (sic) by
the amount of P13,020.00 representing the unpaid obligation of the
defendant to the plaintiff so that the plaintiff is still liable to pay the
defendant the difference in the amount of P32,514.50.
Both parties appealed to
the Court of Appeals. In its Decision
of 28 April 1997, the appellate court set aside the judgment of the trial court
and resolved the case in favor of HOOVEN.
It held that the trial court erred in relying solely on the results of
the ocular inspection since the delivery and installation of the materials in
question started as early as 1981, while the ocular inspection was conducted
only in 1987 or six (6) years later, after the entire mezzanine was altered and
the whole building renovated. The
appellate court also stressed that the testimonies of HOOVEN's witnesses were
straightforward, categorical and supported by documentary evidence of the
disputed transactions, and that all Lagon could offer was a mere denial,
uncorroborated and self-serving statements regarding his transactions with
HOOVEN. The decretal portion of the
assailed decision of the Court of Appeals reads -
ACCORDINGLY, finding the decision of August 26, 1991 appealed from afflicted by reversible errors, the same is hereby SET ASIDE, and a new one entered ordering the defendant-appellant (Lagon) to pay plaintiff-appellant (Hooven Comalco):
The amount of P69,329.00 plus interest of 12% per annum
computed from the date of the filing of the complaint, until fully paid.
Fifteen percent (15%) of the amount due, as and by way of attorney’s fees.
Defendant-appellant to pay costs.
Petitioner's motion for
reconsideration having been denied he now hopes to secure relief from this
Court by contending that: (a) The Court
of Appeals erred in holding that the trial court could not rely on the results
of the ocular inspection conducted on his commercial building in Tacurong,
Sultan Kudarat; and, (b) The assailed decision of the appellate court is based
on speculations and contrary to the evidence adduced during the trial.
The arguments in the
petition ultimately boil down to the sole issue of whether all the materials
specified in the contracts had been delivered and installed by respondent in
petitioner’s commercial building in Tacurong, Sultan Kudarat. The question is basically factual involving
as it does an evaluation of the conflicting evidence presented by the
contending parties, including the existence and relevance of specific surrounding
circumstances, to determine the truth or falsity of alleged facts.
While factual issues are
not within the province of this Court, as it is not a trier of facts and is not
required to examine or contrast the oral and documentary evidence de novo,[6] nevertheless, the Court has the authority to
review and, in proper cases, reverse the factual findings of lower courts in
these instances: (a) when the findings
of fact of the trial court are in conflict with those of the appellate court;
(b) when the judgment of the appellate court is based on misapprehension of facts; and, (c) when the
appellate court manifestly overlooked certain relevant facts which, if properly
considered, would justify a different conclusion.[7] This case falls squarely within the
foregoing exceptions.
Before delving into the
merits of this case, we find it necessary to describe and detail the nature and
contents of the vital documentary exhibits upon which respondent HOOVEN based
its claims, thus -
Exhibit “F” - Undated
Proposal:
I. For the supply of materials and installation of suspended aluminum ceiling runners:
Area: 2,290 sq. ft.
Materials: NU- Main & Cross runners
NU-5 Perimeter mouldings
G.I. wire hangers
Aluminum straps stiffeners
Blind Rivets
and Screws P14,110.00
Labor
charge
4,230.00
18,440.00
II. One (1) set: 65 x 68 YP aluminum cladding 1,150.00
P19,590.00
Delivery and Installation charge 1,860.00
P21,450.00
Exhibit “F-1” – Proposal dated 3 April 1981
“Hooven” Aluminum
Casement Windows Anolok Finish Manually Operated, with 6.0 mm Bronzepane Tinted
Glass
Five (5) sets: 65” x 126-1/2” (w/ transom)
One (1) set: 65” x 126-1/2” (w/ AC provision)
Two (2) sets: 39-1/2” x 125-1/2” -do-
One (1) set: 39-1/2” x 87” -do-
One (1) set: 39-1/2” x 223” -do-
One (1) set: 65” x 57-1/2” (w/ transom)
One (1) set: 65” x 4” -do-
“Hooven” Aluminum
Entrances and Fixed Windows Anolok Finish, with 6.0 mm Bronzepane Tinted Glass
One (1) set: 100-1/2” x 76-1/2”, double sash, double acting swing door, with transom.
Two (2) sets: 80” x 278”, fixed panels 21,740.00
“Hooven” Aluminum
Sliding Windows Fabricated From SD-Sections, Anolok Finish, with 6.0 mm
Bronzepane Tinted Glass
One (1) set: 54 x 191
One (1) set: 45 x
302 11,650.00
75,920.00
Add: Delivery and Installation charge 7,500.00
P83,420.00
Exhibit “A” – Invoice No. 11094 dated 29 December 1982
Eighty Six (86) Pieces, 2.0 mm Hishilite P3,440.00
Diffusers
Exhibit “B” – Invoice No. 11095 dated 29 December 1982
Forty-Three Pieces: For the Supply and
Installation of Light Boxes Fabricated from
GA. 032 Aluminum Plain Sheet
Delivery and Installers’ subsistence P5,718.50
Exhibit “C” – Invoice No. 14349 dated 29 December 1984
Five (5) sets 1.651m 3.213m Hooven Aluminum Casement windows, Anolok finish, manually operated with 6.0 Bronzepane tinted glass.
One (1) set 1.651 m 3.367m - do - with a/c provision
Two (2) sets 1.00 m 3.188m - do - - do -
One (1) set 1.00 m 2.210 m - do - - do -
One (1) set 1.00 m 5.664 m - do - - do -
One (1) set 1.651m 1.461 m - do - - do - with transom
One (1) set 1.651m 1.880 m - do - with transom
One (1) set 1.651m 1.524 m - do - - do -
One (1) set 2.553m 1.943 m Hooven aluminum double sash, double acting swing door, with transom, with 6.0 mm Bronze-pane tinted glass.
Two (2) sets 2.032m 7.061 m Fixed windows, Anolok finish.
One (1) set .737 m 7.061 m Aluminum tubulars with aluminum YP-100 cladding, Anolok finish.
One (1) set 1.143m 4.851m Hooven aluminum sliding windows fabricated from SD sections, Anolok finish, with 6.0 mm Bronzepane tinted glass, with 1.88 m tubular posts.
One (1) set 1.143m 7.671m
- do - P75,291.83
4% tax
3,011.67
78,303.50
Delivery & Subs. 7,500.00
P85,803.50
Exhibit “D” – Invoice No. 14265 dated 29 September 1984
For the supply of
materials and installation of aluminum stucco embossed sheet on spiral
staircase P5,310.00
Exhibit “E” – Invoice No. 14264 dated 29 November 1984
For the supply of materials and installation of suspended aluminum ceiling system.
Materials: NU-4 main and cross runners
NU-5 perimeter mouldings
GI wire hangers
Alum strap stiffeners
Blind rivets
and screws P17,057.00
Exhibit “A-1” – Delivery Receipt dated 9 June 1981
Twenty (20) pieces Light boxes fabricated from aluminum sheets
Forty (40) pieces 2.0 mm x 24” x 24” Hishilite Diffusers
Lump sum cost including discount and Delivery and
Installer Subsistence
P4,340.00
Exhibit “A-2” – Delivery Receipt dated 8 August 1981
Twenty (20) pieces Light boxes fabricated from .032” aluminum plain sheet
Twenty Seven (27) 2.0 mm x 24” x 24” Hishilite Diffusers
Add: Delivery & Installers Subsistence P180.00
Exhibit “A-3” – Delivery Receipt, dated 8 December 1981
19 pcs. 2.0 mm x 2” x2” Hishilite Diffusers P40.00
Exhibit “B-1” – Delivery Receipt dated 25 June 1981
Additional three (3) pcs. Light boxes fabricated from .032 Aluminum sheets
P140.00
Exhibit “C-1” – Delivery Receipt dated 25 August 1983
To change alum tubular frames for sliding windows (item 10 & 11) from 45” L x to 94” x 74.”
To change width of one (1) set: item 1 from 126-1/2 to 132-1/2.
To add: one (1) set 65”H x 60” aluminum casement windows with 6.0 mm tinted glass.
To extend alum tubulars of fixed windows on 2nd floor by
29”L and installation of YP-aluminum cladding P8,640.00
Exhibit “C-2” – Delivery Receipt dated 25 August 1983
Hooven Alum Casement Windows Anolok Finish Manually Operated with 6.0 mm Bronzepane Tinted Glass:
Five (5) sets: 65” x 126-1/2” with transom
One (1) set: 65” x 126-1/2 with AC provision
Two (2) sets: 39-1/2 x 125-1/2 - do -
One (1) set: 39-1/2” x 87” - do -
One (1) set: 39-1/2” x 223” - do -
One (1) set: 65” x 57-1/2” with transom
One (1) set: 65” x 74” - do -
P42,530.00
Hooven Alum Entrances & Fixed Windows Anolok Finish with 6.0 mm Bronzepane Tinted Glass:
One (1) set: 100-1/2 x 76-1/2, double sash, double acting swing door, with transom
Two (2) sets: 80” x 278” fixed panels P21,740.00
Exhibit “C-3” – Delivery Receipt dated 25 August 1983
Hoven Alum Sliding Windows Fabricated from SD Sections Anolok Finish with 6.0 mm Bronzepane Tinted Glass:
One (1) set: 45” x 191”
One (1) set: 45” x 302” P11,650.00
Add: Delivery and Installation 7,500.00
Less: 7% Discount 6,256.50
P77,163.50
Exhibit “D-1” – Delivery Receipt dated 25 August 1983
For the supply of
materials and installation of aluminum stucco embossed sheet on spiral
staircase: One (1) set 32” H x 304” WL
P5,310.00
Exhibit “E-1” – Delivery Receipt dated 25 August 1983
NU- main and cross runners
NU-5 Perimeter mouldings
G.I. Wire Hangers
Aluminum straps stiffeners
Blind rivets and screws P17,057.00
We have carefully and
diligently considered the foregoing exhibits and we are fully convinced that
the mass of documentary evidence adduced by respondent suffers from patent
irregularities and material inconsistencies on their faces, raising serious
questions requiring cogent explanations.
These flaws inevitably deplete the weight of its evidence, with the
result that for lack of the requisite quantum of evidence, respondent dismally
failed in the lower court to discharge its burden necessary to prevail in this
case.
Firstly, the quantity of
materials and the amounts stated in the delivery receipts do not tally with
those in the invoices covering them, notwithstanding that, according to HOOVEN
OIC Alberto Villanueva, the invoices were based merely on the delivery
receipts.[8] For instance, only eleven (11) items were
listed in Exhs. "C-2" and "C-3" with a total worth of P77,163.50. But in Exh. "C," which was the
invoice for Exhs. "C-2" and "C-3," there were thirteen (13)
items enumerated for a total worth of P85,803.50. If Exh. "C" is supposed to be
based on Exhs. "C-2" and "C-3," we cannot understand the
apparent discrepancy in the items listed in those documents when they all
referred to the same materials.
Secondly, the total value
of the materials as reflected in all the invoices is P117,329.00 while
under the delivery receipts it is only P112,870.50, or a difference of P4,458.00. Moreover, the materials listed in the two
(2) Proposals, upon which HOOVEN based its claims, is only for the total
sum of P104,870.00. Curiously
then, why would the materials supposedly delivered by HOOVEN be more than
what was contracted and purchased by Lagon? This circumstance underscores the need to reexamine the strength,
if not weakness, of respondent’s cause.
Thirdly, under the Proposals
HOOVEN bound itself to invoice the materials "when complete and ready for
shipment." Oddly, the records show that the invoices were prepared several
years after the materials were allegedly delivered and installed completely on
petitioner’s building. Alberto
Villanueva testified that their project with petitioner was completed sometime
in August 1981 and that thereafter no further installation was done in the
building.[9] But the disputed invoices marked Exhs.
"A" and "B" were prepared only on 29 December 1982; Exhs.
"C" and "D" were prepared only on 29 December 1984; and,
Exh. "E" was prepared only on 29 November 1984. As for the delivery receipts, Exhs.
"C-1," "C-2," "C-3" and "E-1" were
prepared only on 25 August 1983 or two (2) years after the completion of the
project, while Exh. "A-3" was prepared only on 8 December 1981 or
some four (4) months after the date of completion.
Even more strange is the
fact that HOOVEN instituted the present action for collection of sum of money
against Lagon only on 24 February 1987, or more than five (5) years after the
supposed completion of the project.
Indeed, it is contrary to common experience that a creditor would take
its own sweet time in collecting its credit, more so in this case when the
amount involved is not miniscule but substantial.
Fourthly, the demand
letter of 25 August 1983[10] sent to petitioner by respondent further
betrays the falsity of its claims -
Dear Mr. Lagon:
The bearer, Mr. Fermin Piñero, is an authorized representative of this company. He will arrange for your acceptance of the complete aluminum and glass installation we have undertaken for your building. He has with him the delivery receipts for your signature so with a statement of account showing your balance. Kindly favor us with a partial payment to cover our operation costs. Also kindly relay to him all other installations you wish us to undertake.
Hoping for your favorable action, we shall remain.
Very Truly Yours,
Hooven Comalco Industries, Inc.
Davao Branch
(Sgd.) Alberto P. Villanueva
If, as claimed by HOOVEN,
all the materials were completely delivered and installed in petitioner’s
building as early as August 1981, why then would it demand partial payment only
two (2) years later? This circumstance
is very significant especially considering that under the Proposals the
terms of payment should be 50% down "and the balance to be paid in full"
upon completion. Moreover, it is
surprising that the partial payment demanded was only "to cover operation
costs." As correctly observed by petitioner, demand for payment of
operation costs is typical of a still on-going project where the contractor
needs funds to defray his expenses. If
there was complete installation, why would respondent demand payment for operation
costs only? Why not enforce the whole
amount of indebtedness? All these
clearly suggest that there was no full and complete delivery and installation
of materials ordered by petitioner.
Fifthly, all the delivery
receipts did not appear to have been signed by petitioner or his duly
authorized representative acknowledging receipt of the materials listed
therein. A closer examination of the
receipts clearly showed that the deliveries were made to a certain Jose Rubin,
claimed to be petitioner’s driver, Armando Lagon, and a certain
bookkeeper. Unfortunately for HOOVEN,
the identities of these persons were never been established, and there is no
way of determining now whether they were indeed authorized representatives of
petitioner. Paragraph 3 of each Proposal
is explicit on this point -
3. x x x the seller’s responsibility ends with delivery of the merchandise to carrier in good condition, to buyer, or to buyer’s authorized "Receiver/Depository" named on the face of this proposal (underscoring supplied).
As above specifically
stated, deliveries must be made to the buyer or his duly authorized
representative named in the contracts.
In other words, unless the buyer specifically designated someone to
receive the delivery of materials and his name is written on the Proposals
opposite the words "Authorized Receiver/Depository," the seller is
under obligation to deliver to the buyer only and to no other person;
otherwise, the delivery would be invalid and the seller would not be discharged
from liability. In the present case,
petitioner did not name any person in the Proposals who would receive
the deliveries in his behalf, which meant that HOOVEN was bound to deliver
exclusively to petitioner.
Sixthly, it is also
obvious from the contested delivery receipts that some important details were
not supplied or were left in blank, i.e., truck numbers, persons who delivered
the materials, invoice and s. o. numbers.
The persons who delivered the materials were potential witnesses who
could shed light on the circumstances surrounding the alleged deliveries of the
materials to petitioner. Moreover, it
could have been easier for HOOVEN to pinpoint responsibility to any of its
employees for the non-delivery of the materials.
We are not unaware of the
slipshod manner of preparing receipts, order slips and invoices, which
unfortunately has become a common business practice of traders and
businessmen. In most cases, these
commercial forms are not always fully accomplished to contain all the necessary
information describing the whole business transaction. The sales clerks merely indicate a
description and the price of each item sold without bothering to fill up all
the available spaces in the particular receipt or invoice, and without proper
regard for any legal repercussion for such neglect. Certainly, it would not hurt if businessmen and traders would
strive to make the receipts and invoices they issue complete, as far as
practicable, in material particulars.
These documents are not mere scraps of paper bereft of probative value
but vital pieces of evidence of commercial transactions. They are written memorials of the details of
the consummation of contracts.
Given this pathetic state
of respondent's evidence, how could it be said that respondent had
satisfactorily proved its case?
Essentially, respondent has the burden of establishing its affirmative
allegations of complete delivery and installation of the materials, and
petitioner’s failure to pay therefor.
In this regard, its evidence on its discharge of that duty is grossly
anemic. We emphasize that litigations
cannot be properly resolved by suppositions, deductions, or even presumptions,
with no basis in evidence, for the truth must have to be determined by the hard
rules of admissibility and proof.
The Court of Appeals
however faulted the trial court for supposedly relying solely on the
results of the ocular inspection on the premises, which were not conclusive
since the inspection was conducted several years after the disputed materials
were allegedly installed therein.
We disagree. The ocular inspection was made by the judge
himself, at the request of both petitioner and respondent, for the exclusive
purpose of determining whether the materials subject of this case were actually
delivered and installed. There is
therefore no basis to give little evidentiary value on the results of the
ocular inspection, as the Court of Appeals would, and charge the trial court
with error for relying thereon. It is
now rather late for any of the parties to disclaim them, especially when they
are not in his or its favor.
Furthermore, a cursory reading of the decision of the court a quo
will at once show that it was not premised solely on the results of the ocular
inspection but was likewise predicated on other evidence presented by the
parties and well-considered facts and circumstances discussed by the trial
court in its ratio decidendi. We
cannot ignore the factual findings of the trial court, which must carry great
weight in the evaluation of evidentiary facts, and in the absence of any
indication showing grave error committed by trial court, the appellate court is
bound to respect such findings of fact.
We hasten to add however
that petitioner is not entirely free from any liability to respondent. Petitioner admitted the delivery of
materials under Exhs. "A" and its submarkings, "B" and its
submarkings, "D," "D-1" and "E." With respect to
Exh. "C-2," petitioner acknowledged his obligation under the first
heading, Items Nos. 3, 4 and 5, and the second heading, and denied the rest. Consequently, he should be made liable
therefor in the total amount of P58,786.65. From this amount, petitioner’s down payment of P48,000.00
should be deducted.
It is insisted by
petitioner in his appeal brief filed before the Court of Appeals that the
second item under the second heading of Exh. "C-2" should be excluded
in the computation since he never admitted liability therefor.
We are not
persuaded. The transcript of
stenographic notes shows that during the ocular inspection counsel for
respondent manifested in effect that petitioner admitted the delivery and
installation of the second item in his building, and petitioner did not
interpose any objection to respondent's manifestation -
ATTY. QUIÑONES: We would like to make of record that defendant (Lagon) admits that plaintiff (Hooven Comalco) delivered and installed Item No. 1 under the second column of Exhibit “C-2” which is the front door of the ground floor.
ATTY. RICO: Defendant however adds that these were installed in 1981 and had already paid for the said item.
ATTY. QUIÑONES: I would like to make of record also that defendant admits the delivery and installation of Item No. 2 under the second column of Exhibit “C-2” as having been delivered and installed by the plaintiff in 1981 with the qualification, however, that he had already paid the same.
COURT: Are you stating that all these installed items on the ground floor were all paid by you?
MR. LAGON: Yes, Your Honor.[11]
Petitioner cannot now be
heard to complain against its inclusion in the computation of his liability
since his silence virtually amounted to acquiescence. The silence of one of the contracting parties and his failure to
protest against the claims of the other party, when he is chargeable with the
duty to do so, strongly suggest an admission of the veracity and validity of
the other party’s claims.
In sum, petitioner’s
total liability to respondent may be computed as follows:
(1) Items under Exh. “A,” consisting of 17
light diffusers at P40.00 each P 680.00
(2) Items under Exh. “B,” consisting of 23
light boxes at P40.00 each 3,220.00
(3) Third, fourth and fifth items under the first
heading of Exh. "C-2" which on the basis of
their measurements constitute only 1/3 of
the total costs of materials listed therein 14,176.65
(4) Items under the second heading of
Exh. “C-2” 21,740.00
(5) Items under Exhs. “D” and “D-1” 4,860.00
(6) Items under Exh. “E-1” 14,110.00
P58,786.65
Less: Stipulated 7% discount 4,408.99
P54,377.66
Less: Advance payment made by petitioner
to Hooven Comalco
48,000.00
Unpaid Balance of petitioner P6,377.66
Notwithstanding the
breach of contract by respondent in failing to deliver and install in the
premises of petitioner all the stipulated materials, we nevertheless accede to
the right of respondent to recover the unpaid balance from petitioner for the
materials actually delivered.
The next point of inquiry
is the propriety of awarding damages, attorney’s fees and litigation expenses.
We are not in accord with
the trial court’s ruling that petitioner is entitled to actual damages to the
extent of the undelivered materials and undone labor in the amount of P26,120.00. There is no proof that petitioner already
paid for the value of the undelivered and uninstalled materials to
respondent. Therefore, petitioner may
not be deemed to have suffered any such damage. We have declared in no uncertain terms that actual or
compensatory damages cannot be presumed but must be proved with reasonable
degree of certainty.[12] A court cannot rely on speculations,
conjectures or guesswork as to the fact of damage but must depend upon
competent proof that they have indeed been suffered by the injured party and on
the basis of the best evidence obtainable as to the actual amount thereof.[13] It must point out specific facts that could
provide the gauge for measuring whatever compensatory or actual damages were
borne.
But we agree with
petitioner that he is entitled to moral damages. HOOVEN's bad faith lies not so much on its breach of contract -
as there was no showing that its failure to comply with its part of the bargain
was motivated by ill will or done with fraudulent intent - but rather on its
appalling temerity to sue petitioner for payment of an alleged unpaid balance
of the purchase price notwithstanding knowledge of its failure to make complete
delivery and installation of all the materials under their contracts. It is immaterial that, after the trial,
petitioner was found to be liable to respondent to the extent of P6,377.66. Petitioner's right to withhold full payment
of the purchase price prior to the delivery and installation of all the
merchandise cannot be denied since under the contracts the balance of the
purchase price became due and demandable only upon the completion of the
project. Consequently, the resulting
social humiliation and damage to petitioner's reputation as a respected
businessman in the community, occasioned by the filing of this suit provide
sufficient grounds for the award of P50,000.00 as moral damages.
Moreover, considering the
fact that petitioner was drawn into this litigation by respondent and was
compelled to hire an attorney to protect and defend his interest, and taking
into account the work done by said attorney throughout the proceedings, as
reflected in the record, we deem it just and equitable to award attorney's fees
for petitioner in the amount of P30,000.00.[14] In addition, we agree with the trial court
that petitioner is entitled to recover P46,554.50 as actual damages
including litigation expenses as this amount is sufficiently supported by the
evidence.[15]
WHEREFORE, the assailed Decision of the Court of
Appeals dated 28 April 1997 is MODIFIED.
Petitioner Jose V. Lagon is ordered to pay respondent Hooven Comalco
Industries, Inc., P6,377.66 representing the value of the unpaid
materials admittedly delivered to him.
On the other hand, respondent is ordered to pay petitioner P50,000.00
as moral damages, P30,000.00 as attorney's fees and P46,554.50 as
actual damages and litigation expenses.
SO ORDERED.
Mendoza, Quisumbing,
Buena and DeLeon Jr., JJ., concur.
[1] Decision penned by Associate Justice B. A. Adefuin-de la Cruz,
concurred in by Associate Justices Gloria C. Paras (now retired) and Ricardo P.
Galvez (now Solicitor General).
[2] Resolution penned by Associate Justice B. A. Adefuin-de la Cruz,
concurred in by Associate Justices Consuelo Ynares-Santiago (now Supreme Court
Justice) and Presbitero J. Velasco, Jr.
[3] Exhs.
“F” and “F-1.”
[4] Exh.
“G.”
[5] 26
August 1991 Decision penned by Judge Romeo D. Marasigan, RTC-Br. 16, Davao
City.
[6] See
Imperial v. Court of Appeals, G.R. No. 102037, 17 July 1996, 259 SCRA 65, 71.
[7] Reyes
v. Court of Appeals, G.R. No. 110207, 11 July 1996, 258 SCRA 651.
[8] TSN, 8
September 1988, p. 98.
[9] TSN, 2
June 1989, pp. 243-244.
[10] Exh.
“H.”
[11] TSN, 9
October 1987, pp. 12-13 (Ocular Inspection).
[12] Del
Mundo v. Court of Appeals, G.R. No. 104576, 20 January 1995, 240
SCRA 348; Development Bank of the Philippines v. Court of Appeals, G.R.
No. 110053, 16 October 1995, 249 SCRA 331; Del Rosario v. Court of Appeals,
G.R. No. 118325, 29 January 1997, 267 SCRA 158, 171.
[13] Del
Rosario v. Court of Appeals, id.
[14] Art.
2208. In the absence of stipulation,
attorney’s fees and expenses of litigation, other than judicial costs, cannot
be recovered, except: (1) When exemplary damages are awarded; (2) When the
defendant’s act or omission has compelled the plaintiff to litigate with third
persons or to incur expenses to protect his interest; (3) In criminal cases of
malicious prosecution against the plaintiff; (4) In case of a clearly unfounded
civil action or proceeding against the plaintiff; (5) Where the defendant acted
in gross and evident bad faith in refusing to satisfy the plaintiff’s valid,
just and demandable claim; (6) In actions for legal support; (7) In actions for
the recovery of wages of household helpers, laborers and skilled workers; (8)
In actions for indemnity under the workmen’s compensation and employer’s
liability laws; (9) In separate civil action to recover civil liability arising
from a crime; (10) When at least double judicial costs are awarded; and (11) In
any other case where the court deems it just and equitable that attorney’s fees
and expenses of litigation should be recovered. In all cases, the attorney’s fees and expenses of litigation must
be reasonable (New Civil Code).
[15] The
trial court erroneously computed the amount of litigation expenses it awarded
to petitioner; instead of P45,534.50 it should be P46,554.50.